Client: Saint
Peter’s Medical Center, New Brunswick, NJ
Contact:
Mr. Alexander Chaykoski
Project:
Replace Existing Chillers
Background
– The main
chilled water source for this 400-bed medical center consisted of two, 30-year
old, 600-ton single stage steam absorption chillers, which were plagued with
operational problems and straining to keep up with the load of an expanding
facility. When one of the chillers
failed in the peak cooling season,
patient comfort was significantly impacted.
Intent
– The client wanted to replace the chillers to provide a reliable chilled
water plant with increased capacity to keep up with facility expansion.
Operating cost was also a concern.
Conceptual
Challenges –
1) To increase chiller capacity without increasing energy consumption.
2) To complete the installation within the winter months.
3) To work around an antiquated electrical switch gear/motor control
center, which supplied power to all major equipment in the power plant, with no
interruption of the steam heating plant. 4)
To demolish existing equipment next to the boilers without interrupting boiler
operation. 5) To rig large, heavy new equipment into a limited space with a
floor level 6 feet below grade.

Details –
1) The existing units were replaced with single 1060-ton and 740-ton, two stage
absorption chillers. 2) The side of
the building was removed, cribbing was installed, and the chillers were hoisted
and rolled onto the cribbing. A
hole was created in the roof and the chillers were again hoisted, the cribbing
removed and they were lowered to the floor and rolled
into place. 3) A new motor control
center was installed and new chilled water pumps were installed.
Results
– 1) Because the new chillers were two-stage absorption chillers, the client obtained 1800 tons of capacity with no increase in
steam consumption. 2) The project
was completed on time and within the $1.25 million budget.
3) The client was appreciative of
the attention to detail provided by BUIST.
4) The shipment of the
chillers from overseas was delayed, but by prefabricating a large portion of the
piping, BUIST was able to complete the project before the cooling season.
5) Permission to speak with the client may be arranged upon request.