Client: Dun
& Bradstreet, Berkeley Heights, NJ
Contact:
Mr. Fred Tabertshofer
Project:
Replace Existing Chillers
Background
– Dun
& Bradstreet maintains a major data processing center in Berkeley Heights,
NJ. The chilled water plant, which
is vital for the mainframe computers as well as providing environmental control
for historical data storage, consisted of two, 30-year old water cooled
chillers, and two 15-year old air cooled chillers.
Interruption of the chilled water system results in a cost to production
of $50,000 per hour, and can cause unpredictable data errors and associated
start-up problems.
Intent
– The client wanted to replace the chillers to provide a reliable chilled
water plant with redundancy. Elimination
of the chloro-fluorocarbon refrigerants, which are known to damage the ozone
layer, operational energy savings and the ability to take advantage of available
energy rebates were also objectives.
Conceptual
Challenges –
1) To site and install the new equipment while the existing remained in
operation. 2) To complete the
installation within a limited timeframe to take advantage of rebates before they
were phased out. 3) To modify the
existing underground chilled
water storage
tank
piping with minimum interruption to redundancy, and
no interruption of the chilled water system’s end use.
4) To replace the complicated, installed piping system with a simple,
redundant system. 5) To accomplish the piping changeover to the new system with
no interruption of the chilled water system.
6) To keep the cooling tower in service during construction.
Details –
1) Space for the new chillers was created by constructing a building addition.
2) A new cooling tower was installed and temporarily piped to allow
demolition of the old tower. 3) The
chilled water system was changed to a de-coupled primary/ secondary variable
frequency drive system to reduce system pressure, increase energy efficiency and
increase redundancy. 4) Chilled
water piping to the critical area was installed with welded joints, while
grooved joint piping was eliminated for increased reliability.
5) The connection to the new chilled water system was accomplished by
providing hot taps downstream of the tie-in points with temporary piping to
those points from the new system. The
piping in between the hot taps and the tie-in points was then frozen, so the
permanent connections could be made. 6)
The project cost was
approximately $2.6
million for which BUIST was responsible for half.
Results
– 1) The project was completed on time and within budget.
2) There was no interruption of services.
The reliability of the chilled water system was greatly increased by the
design changes implemented. 3) The
energy rebate was secured because the project was completed on time.
4) The client’s Project Engineer was pleased with the system pressure
reduction and the redundancy afforded by the primary/secondary pump system.
5) Permission to speak with the client may be arranged upon request.